Albany International Airport

Our efficient and productive erection crew did “catch up” to the pile driving/ foundation pouring operation yet was able to work in conjunction with the general contractor and precast fabricator to resequence the panel erection operation in order to allow the delivery of precast product to keep moving to the crane.